1. Improvement of Bagerhat-Rampal-Mongla District Highway to Appropriate Level of Standard and Width.

(WP-01) : Widening, Construction of New Pavement, Strengthening, Surfacing (DBS), Construction of Rigid Pavement, Retaining Wall, Protective work, RCC/ PC Girder Bridge (2 Number), RCC Box Culvert (8 Number), Road Marking, Sign Signal, installation Guard Rail/W Beam, Guide Post, Kilometer Post and 1 number Number Intersection Development from Ch. 0+000m to 10+000m of Bagerhat-Rampal-Mongla District Highway (Road No. Z-7717) under  Road Division, Bagerhat during the year 2021-2022. 

(WP-02) : Widening, Construction of New Pavement, Strengthening, Surfacing (DBS), Construction of Rigid Pavement, Retaining Wall, Protective work, RCC/ PC Girder Bridge (2 Number), RCC Box Culvert (4 Number), Road Marking, Sign Signal, installation Guard Rail/W Beam, Guide Post, Kilometer Post and Construction 2 number Bus-Bay from Ch. 10+000m to 18+251m of Bagerhat-Rampal-Mongla District Highway (Road No. Z-7717) under  Road Division, Bagerhat during the year 2021-2022.

(WP-03) : Widening, Construction of New Pavement, Strengthening, Surfacing (DBS), Construction of Rigid Pavement, Retaining Wall, Protective work, PC Girder Bridge (1 Number), RCC Box Culvert (3 Number), Road Marking, Sign Signal, installation Guard Rail/W Beam, Guide Post, Kilometer Post, 1 Number Ferry Ghat with Approach Road,  1 number Intersection Development & Construction 2 Number Bus-Bay from Ch. 18+251m to 22+875m of Bagerhat-Rampal-Mongla District Highway (Road No. Z-7717) under  Road Division, Bagerhat during the year 2021-2022.

(WP-04) : Widening, Construction of New Pavement, Strengthening, Surfacing (DBS), Construction of Rigid Pavement, Retaining Wall,Protective work, RCC/ PC Girder Bridge (3 Number), RCC Box Culvert (6 Number), Road Marking, Sign Signal, installation Guard Rail/W Beam, Guide Post, Kilometer Post, Construction 2 number Bus-Bay & Installation 1 number Ferry Ghat from Ch. 22+875m to 33+828m of Bagerhat-Rampal-Mongla District Highway (Road No. Z-7717) under  Road Division, Bagerhat during the year 2021-2022.

Work Start Date : 01 July, 2021

Work Completion Date : 30 Jun, 2024

 

 

2. Construction of Concrete Bridge in existing Narrow & Damaged concrete Bridge/Bailey on Highways under Khulna Zone.

প্রকল্পের খুলনা জোনের বাগেরহাট সড়ক বিভাগের  অধীন ০৪ (চার) টি প্যাকেজের আওতায় ২৩ (তেইশ) টি নতুন ব্রিজের নির্মাণ কাজ চলমান রয়েছে।

Work Start Date : 18 August, 2021

Work Completion Date : 17 Novembe, 2023